Town of Blowing Rock Seal
Town of Blowing Rock Seal 2:16pm
Town of Blowing Rock Seal
Helpful Links
Other Links


Water / Wastewater

7190 Valley Blvd, Hwy. 321
PO Box 47
Blowing Rock, NC 28605

Ph:(828) 295-5225 (Water Plant) Fax:(828) 295-5202
Ph:(828) 295-5226 (Sewer Plant) Fax:(828) 295-5202

Mr. Tom McRary, Director of Plant Operations
Mr. Mike Wilcox, Director of Field Operations

DEPARTMENT:  Water and Sewer Plant and Field Operations 

 

 

Description and Responsibilities

 

The Water and Sewer Department is responsible for the operation of a Water Treatment Plant, the operation and maintenance of the water distribution system, the operation of a Wastewater Treatment Plant, and the operation and maintenance of the wastewater collection system.

 

Water Plant

The 1.0 MGD Water Treatment Plant (expandable to 2.0 MGD) was constructed in 1978 and receives water from the Town’s 45-47 million gallon pond on Brickhouse Creek, with Chetola Lake serving as a backup water source during times of drought. The plant is located along U.S. Highway 321 just south of the Blue Ridge Parkway. The facility is a traditional treatment process including alum addition, flocculation, settling and filtration. Corrosion control is also utilized prior to distribution to the residents using phosphates.

The Town’s service area is entirely south of the Water Treatment Plant. Finished water is pumped to a high elevation, then allowed to gravity feed into the service area. The Green Hill tank, capacity 3.0 MGD, is the means of control at the highest point of the system. A number of pressure reducing valves have been placed in the system to control maximum pressures for the residents.

 

The Town has actively sought new water sources, which may prove to be more reliable. In times of drought and high demand, the current source is of inadequate quantity. At this time, the Town of Blowing Rock is under restrictions imposed by North Carolina Department of Environment and Natural Resources restricting development, which would result in additional water service connections. In 2008, the Town executed a water agreement with the Town of Boone for an emergency water system interconnection. This project is currently under construction and should be completed during this fiscal year.

 

Wastewater Treatment Plant

The Town of Blowing Rock operates a Wastewater Treatment Plant very near the Water Treatment Plant and utilizes a discharge to the Middle Fork of the New River. The plant is rated for capacity of .800 MGD, but could be expanded to a service capacity of 1.2 MGD. The original plant was constructed in 1960 and refurbished and expanded in 1989. The facility is fed by four (4) sewer system lift stations that handle the entire volume of wastewater generated by the community. The facility is of concrete construction and is set up for extended aeration treatment. The plant operators sample the water discharge everyday and also send samples out three times per week to an independent testing lab to insure environmental compliance.

 

Water & Sewer Field Operations Division

The Field Operations division is responsible for all water and sewer taps, leak repair and water line installation. This department is also responsible for all water meter reading in the town on a bi-monthly basis. In addition, this department maintains the water distribution system and the wastewater collection system.

 

There are approximately 2,205 water meters and 1,722 sewer taps in the system. The water distribution system consists of approximately 22 miles of lines. The wastewater collection system consists of approximately 15.8 miles of gravity sewer lines and 3.4 miles of pressure sewer. There are four (4) wastewater lift-stations: Mayview, Chetola, Chestnut and Quail Hollow.

 

Staffing and Schedules

 

A Director of Water & Wastewater Plant Operations, two (2) Senior Plant Operators, and a Plant Operator are assigned to Water Plant and Wastewater Plant Divisions. The personnel work a varied schedule to meet the service demands of the utility.

 

Three (3) Heavy Equipment Operators and an Equipment Operator I are assigned to the Water & Sewer - Field Operations Division. The division uses other employees, as needed, for the reading of water meters.  The personnel work a standard 40 hour week schedule and are on call for emergency repairs.

 

Measures of Activity

 

2008/2009 Wastewater Plant - Average Daily Flow                                 2008/2009 Water Plant - Total Water Treated

 

Month

2008

Average Daily

(.800 MGD capacity)

2009

Average Daily

(.800 MGD capacity)

 

 

Month

2008

Total Water Treated

(Million Gallons)

2009

Total Water  Treated

(Million Gallons)

January

.212

.253

January

16.8121

10.2958

February

.224

.166

February

13.6414

8.8206

March

.304

.180

March

13.6908

8.5464

April

.207

.266

April

14.5086

8.7979

May

.194

.435

May

15.8770

9.7860

June

.196

.409

June

13.4592

12.0500

July

.286

.255

July

16.8341

14.5137

August

.260

.260

August

15.7925

12.0820

September

.278

.316

September

13.7923

11.9136

October

.248

.346

October

13.5381

12.4491

November

.215

.322

November

9.5318

9.1295

December

.280

.364

December

12.0888

11.6520

 

 

 

TOTAL

169.5667

130.0366

TOTAL TREATED

88.550 MG

108.592 MG

MONTHLYAVERAGE

14.1305

10.8364

 

Designed by ARDI Valid XHTML 1.0! Valid CSS!